Work to begin on £1.2m A483 Wrexham Road improvement scheme

13 September 2017

A £1.2m scheme to improve traffic flow on the A483/Wrexham Road route into Chester will begin on Monday, 25 September.

The works will widen the A483 inbound from a dual carriageway to a three lane road between Posthouse roundabout and the Chester Business Park.

The work is expected to take 10 weeks and aims to improve traffic flow on the A55, as well as the A483, by allowing traffic to leave the roundabout more speedily.  It will be carried out by contractors, King Construction.

Traffic management will only be in place during off-peak hours to minimise disruption.  Between the hours of 6.30am and 9am, and again from 4.30pm to 6.30pm two lanes of traffic will be maintained where possible.

During the works the road will have a temporary 30mph speed restriction and the right turns into the Holiday Inn, and the petrol station next to it, will be temporarily closed until the scheme is completed.

A second phase of the scheme will involve resurfacing the A483 from the Heron’s Way roundabout, running adjacent to The King’s School and up to a point just before Nuffield Health’s Grosvenor Hospital.  However, work on this section will not begin until the school half term holiday (from Friday 20 October) and will be carried out during nights only.

The Council’s Cabinet Member for Environment, Councillor Karen Shore said: “The A483 Wrexham Road is one of the main commuter routes into and out of Chester.  The scheme includes widening and resurfacing the route and unfortunately this means that motorists will experience some disruption from 25 September, for around 10 weeks, but once the scheme is finished the benefits will be obvious.

“We will try to minimise traffic disruption by carrying out the work outside of peak hours, including working overnight, and we would ask people to bear with us whilst we make these improvements.

“We are committed to easing traffic congestion on the A483/Wrexham Road into Chester which has become a source of frustration for motorists and is in conflict with our plans to grow Chester’s economy over the coming years.” The Council successfully applied for funding for the scheme through the National Productivity Investment Fund from the Department for Transport.

Andy Withington, North West Asset Delivery Manager at Highways England, said: “We’ve been working closely with Chester West and Cheshire Council to identify improvements that can be made to tackle congestion on the road into Chester, and are pleased that the council has been able to secure funding to add an extra lane to the A483.

“The scheme will support the project we carried out a couple of years ago at the Posthouse roundabout and will help improve the flow of traffic for drivers who use the busy route between Wales and Cheshire.”

More information about the scheme will be available on the Council website.
 

Discuss this article

Please see terms below before using this feature
Please be aware that the facility above is a Facebook service, posting your views will make some of your Facebook information visible to everyone (as with any Facebook activity).

The system administrators (VISAV Limited) monitor the content added. Any misuse or objectionable material should be reported to support@neighbourhoodalert.co.uk.

The views expressed do not represent the views of the system administrators who are VISAV Limited, the Police, Neighbourhood Watch and other Information Provider using this service. The System Administrators make no guarantee, endorsement and accept no liability, regarding the discussion service above, including, but not limited to, its availability, accuracy, currency, content, quality or lack of objectionable or offensive content.

© 2017 Cheshire West and Chester. All rights reserved.