Update on overnight works on St. Martins Way Chester 13 to 17 December

1 December 2021

As part of the current works in the city centre to reinstate the highway following the construction of a new surface rainwater drain, and to reduce the impact on traffic during the day; the following overnight works and road closures will take place:
  • Monday 13 December – overnight from 8pm to 6am – Planing (removal of old road surface) on St. Martins Way southbound in front of new Northgate car park and Princess Street. Martins Way will remain open northbound
  • Tuesday 14 December – overnight from 8pm to 6am – Planing (removal of old road surface) on St. Martins Way northbound between Watergate Street junction and Sens Close. Requiring the closure of St. Martins Way northbound with diversions in place St. Martins Way open southbound from Hunter Street to Grosvenor Roundabout
  • Wednesday 15 December – overnight from 8pm to 6am – Resurfacing St. Martins Way northbound between Watergate Street junction and Sens Close.Requiring the closure of St. Martins Way northbound with diversions in place St. Martins Way open southbound from Hunter Street to Grosvenor Roundabout
  • Thursday 16 December – overnight from 8pm to 6am – Resurfacing Princess Street.Martins Way will remain open northbound.

To help minimise the impact, the contractors will strive to ensure that the most noisy and disruptive works are carried out between 8pm and 10:30pm where possible each evening.

They will also aim to maintain access to and from Princess/Trinity Street, Hunter Street and Sens Close, although some delays may be experienced while the works are underway and to ensure safety while equipment is moved out of the way.

Councillor Karen Shore, Deputy Leader of the Council and Cabinet Member – Environment, Highways & Strategic Transport said: “By scheduling these resurfacing works overnight we will reduce delays for traffic during the day and help keep Chester open for business in the run up to Christmas. 

“Please be assured we are working with the contractor to ensure that this final stage can be completed as quickly as possible.”
For more details on the Clockwise diversions to the inner ring-road and why the council is building a new surface water drain with many future-proof environmental benefits (including the current issue of reducing the number of untreated sewage discharges into the River Dee when the current network is already at capacity) please see: www.clockwisechester.com 
 

Discuss this article

Please see terms below before using this feature
Please be aware that the facility above is a Facebook service, posting your views will make some of your Facebook information visible to everyone (as with any Facebook activity).

The system administrators (VISAV Limited) monitor the content added. Any misuse or objectionable material should be reported to support@neighbourhoodalert.co.uk.

The views expressed do not represent the views of the system administrators who are VISAV Limited, the Police, Neighbourhood Watch and other Information Provider using this service. The System Administrators make no guarantee, endorsement and accept no liability, regarding the discussion service above, including, but not limited to, its availability, accuracy, currency, content, quality or lack of objectionable or offensive content.

© 2022 Cheshire West and Chester. All rights reserved.